Introduction to Accessories of Mobile Concrete Mixing Plants

Introduction to Accessories of Mobile Concrete Mixing Plants Introduction to Accessories of Mobile Concrete Mixing Plants Mobile ...

2023年4月26日星期三

Please receive the concrete mixing plant installation instructions


1. Installat
ion

Installation site should be plain and well-grounded. The pithead should be higher than ground to prevent the water inflow.

Lift the mixer with lifting device and install four supporting legs connecting angle inclined strut ladder and the downward track. Then place the mixer in the appropriate place of the pit.

2. Inspection and preparation before test

Check if the connection of the motor and electric element is steady. 

Check connecting bolts between two parts(especially the moving parts) and ensure they are firm. If not tight them up in time. 

Check if there are sundries stuck in mixing canister and track rack.

3. No-load test

Start mixing motor. At the same time the running direction of two mixing shafts should be same with indicating direction of the signs . If there is any difference change the power connection.

4. Over-load test

Shut down the discharge door and lift the hopper after feeding. Insure that the hopper can run steadily and stop on the track freely. If there is slipping you should put the hopper into the pit bottom then adjust the big nut in brake motor.

Attention:

1. Focus on the maintenance of quick-wear parts and reserve appropriate spare parts.

2. When the machine is on maintenance adjustment or cleaning cut off the total power switch and hang a warning sign.

3. Contact with local power supply departments and require them to supply reliable electric power . 

4. There must be an experienced electrician who is responsible for the daily maintenance of electrical equipment specially.

5. If the plant installed is taller than the surrounding buildings or equipment the lightning protection facilities should be collocated.

6. All the safety signs shall be inspected at least once every six months. If there is any damage deformation color fading etc. the signs should be repaired or replaced in time.

By the time you are paying attention to us, our construction equipments are being delivered /distributed to the world everyday - it’ll be such a great honor if you can join usweb: www.smachine1983.com Email: market@smachine1983.com